Sample projectBasement Media Room + Half Bath

Report

Project report

Built from confirmed documents only. Use your browser's print dialog to save it as a PDF.

Demo overview

For a clean PDF, turn off “Headers and footers” in your browser’s print settings.

ScopeCheckupSample project

Report generated March 12, 2026

Project report

Basement Media Room + Half Bath

Sample Renovation Co.

Financial position

Every total is calculated by ScopeCheckup from your confirmed documents.

Current committed total
$49,930

Original contract plus approved changes

Outstanding invoiced amount
$19,550

Total invoiced minus payments recorded

Remaining project commitment
$49,930

Current committed total minus total paid

Original contract total

Confirmed baseline quote total — not the estimate entered at project creation

$47,880

Approved changes

Approved change-order amounts only — change orders are never counted as invoices

$2,050

Current committed total

$49,930

Total invoiced

Invoice documents only

$19,550

Total paid

Payments you have recorded

$0

Outstanding invoiced amount

Total invoiced minus payments recorded

$19,550

Not yet invoiced

Current committed total minus total invoiced

$30,380

Remaining project commitment

$49,930

Documents reviewed

Change orders are tracked separately and are never counted as invoices.

Accepted quote

Accepted quote

$47,880

January 18, 2026

Confirmed invoices

Invoice #1

$19,550

March 4, 2026

Confirmed change orders

Change order #1

$2,050

February 21, 2026

Findings

Every finding is listed with the document it came from, its source pages and its current status.

Invoice #1

7 findings

Matches agreed scope

Matches agreed scope.

Half-bath fixture allowance

Difference

No change

Quoted
$5,000
Current
$5,000

This charge matches the amount in the accepted quote.

QuoteAccepted quotep.3
CurrentInvoice #1p.1
Confidence
High confidence
Resolution
Resolved
Change approval
Not applicable
Matches agreed scope.

Interior painting

Difference

No change

Quoted
$3,900
Current
$3,900

This charge matches the amount in the accepted quote.

QuoteAccepted quotep.3
CurrentInvoice #1p.2
Confidence
High confidence
Resolution
Resolved
Change approval
Not applicable

Price or quantity changed

Price or quantity changed.

Electrical work

Difference

+$450

Quoted
$5,200
Current
$5,650

This amount differs from the original quote.

QuoteAccepted quotep.2
CurrentInvoice #1p.1

Ask your contractor about this difference.

Confidence
High confidence
Resolution
Open
Change approval
Pending

New or unclear item

New or unclear item.

Dedicated AV power circuit

Difference

Not comparable

Quoted
No baseline amount
Current
$850

This item does not clearly match a line in the accepted quote, so there is no baseline amount to compare it against.

QuoteNot found in the accepted quote
CurrentInvoice #1p.2

Ask whether this circuit was part of the agreed electrical scope or added later.

Confidence
Medium confidence
Resolution
Open
Change approval
Pending

Needs your confirmation

Needs your confirmation.

Flooring progress

Difference

Not comparable

Quoted
$6,300
Current
$3,150

This charge appears to bill part of a broader flooring scope totaling $6,300 in the accepted quote. The quote does not state how that scope is split across billings, so the two amounts cannot be compared directly.

QuoteAccepted quotep.3
CurrentInvoice #1p.1

Confirm what portion of the flooring scope this charge represents.

Confidence
Medium confidence
Resolution
Open
Change approval
Pending
Needs your confirmation.

Decorative acoustic slat wall treatment

Difference

Not comparable

Quoted
No baseline amount
Current
$1,200

This item appears to relate to work listed as excluded in the accepted quote. Confirm whether this work was separately approved.

QuoteAccepted quotep.4
CurrentInvoice #1p.2

Ask which written approval covers this work, since the quote lists it as excluded.

Confidence
Medium confidence
Resolution
Open
Change approval
Pending
Needs your confirmation.

Media niche framing

Difference

Not comparable

Quoted
No baseline amount
Current
$650

Related framing scope appears in the accepted quote, but no separate price is stated for it, so there is no baseline amount to compare against.

QuoteAccepted quotep.2
CurrentInvoice #1p.1

Ask whether this framing was already included in the quoted carpentry scope.

Confidence
Low confidence
Resolution
Open
Change approval
Pending

Change order #1

1 finding

Needs your confirmation

Needs your confirmation.

Decorative acoustic slat wall upgrade

Difference

Not comparable

Quoted
No baseline amount
Current
$1,200

This item appears to relate to work listed as excluded in the accepted quote. Confirm whether this work was separately approved.

QuoteAccepted quotep.4
CurrentChange order #1p.1
Confidence
High confidence
Resolution
Resolved
Change approval
Approved

ScopeCheckup organizes project documents and highlights differences for informational purposes. It does not determine whether a charge is valid and does not provide legal, financial, construction or professional advice.

Get a report like this for your own project.

Check My Quote Free